The contaminated land planning condition was attached to the decision notice as the proposed erection of a dwelling is considered to be a sensitive development (contamination is assumed unless proven otherwise).

The site formed part of the garden of the adjacent dwelling as well as part of an orchard. A number of potential sources of contamination (adjacent electricity sub-station, worked coal seams etc.) were identified and discounted as part of the risk assessment.

Given the risks arising from use of the site as an orchard could not discounted, as part of the walkover survey the site soils were sampled and demonstrated the site was not impacted by elevated levels of contamination.

The report was accepted by the local authority and the condition discharged.

  • Head Office

    Hanover House
    Hanover Street
    Liverpool L3 3DZ
    0151 521 2539
    0151 909 3661
    enquiries@demeter-environmental.co.uk
  • Brighton Office

    Gemini House
    136-140 Old Shoreham Road Brighton
    East Sussex BN3 7BD
    01273 741 727
    brighton@demeter-environmental.co.uk