Residential Development, Acorn Park, Rushy Moor Lane, Askern, Doncaster, South Yorkshire
Case Study Reference: 13-09-01
Planning Authority: Metropolitan Borough of Doncaster
Planning Reference: 10/02883/OUT
Synopsis:
Due ot the sensitive nature of the development, the planning authority attached a contaminated land planning condition to the decision notice. The first requirement of the condition was a Phase I Desk Study report.
No credible sources of contamination were identified form the review of the environmental data and historical O.S. maps, and the walkover revealed a fuel tank to the present on site. The observations made during the walkover survey we sufficient to demonstrate the oil tank was not a credible source and the report concluded that no further works were required.
Demeter Environmental were commissioned to prepare the desk study report for the site
The desk study report can be accessed from here.