Given the sensitive nature of the development (residential) and the history of the site a contaminated land planning condition was attached to the decision notice for the proposed development. The first stage of discharging the condition was to prepare a Phase I desk study report in order to determine if the site has the potential […]
-
The contaminated land reports prepared by others prior to the commencement of the development concluded that gas protection measures were required to be installed in order to break the pollution linkages associated with the accumulation of ground gases in the proposed development. Demeter Environmental were commissioned to validate the installation of the gas protection measures […]
-
A desk study report was prepared by others in February 2018 which proposed that further investigation and ground gas monitoring was required. Demeter Environmental Ltd were commissioned to undertake the further works, given that the scope of works was not given in the desk study report the first stage was to reassess the information held […]
-
In order to support the application for the residential redevelopment of a parcel of land adjacent to the Lancaster Canal, a Phase I Desk Study report was required to support the application and to assess the potential for the site to be impacted by elevated levels of contamination. The first stage of the preparation of […]